Challenge

A major upstream operator needed to plan a specific equipment installation during a turnaround. The activity was highly complex, time-intensive, and expensive, requiring careful coordination across disciplines within a constrained execution window.


Solution

The Operator deployed Kognitwin's enhanced operations workflows to support complex turnaround planning.

Key capabilities used:

  • Integrated access to work order and scheduling data

  • Data visualisation dashboards to support maintenance execution

  • 3D models and photogrammetry to plan and map installation routes 

Results
  • Reduced maintenance planning spend by avoiding additional costs to sites and replanning

  • Improved planned vs estimated job accuracy by early identification of logistical restraints

  • Combined with other workflows, the operator avoided more than 4 hours of potential unplanned downtime during start-up